In June 2025 TACROM in cooperation with KazGeoTech has successfully completed the running and cementing operation for the 7x 9 5/8 Rotatable Liner Hanger system for one of our valued customer.
This project required close coordination between our field team, engineering support, and client representatives to ensure smooth execution at every stage — from pre-job planning and equipment preparation to final pressure tests and well integrity confirmation.
The job was done in very short timing; we had 4 weeks from the date of getting an order till running on the field.
Key Highlights:
- Operation Type: Rotatable 10k rated 7" x 9 5/8" liner hanger system
- Equipment Used: RANGER Liner Hanger, SCOUT Liner Top Packer, Hydraulic Running Tool
- Zero Incidents: Safe execution from start to finish
- Customer Satisfaction: Rated “Excellent” in post-job survey
- Team Effort: Field crew, engineering, and client working together
We are proud of our team’s dedication and professionalism, which continue to be the foundation of our success in well completion projects.